Thursday, May 30, 2019

May 30, 2019

South Bend School District
New Elementary School Construction


Rognlin's Inc. has begun mobilization of heavy equipment and started building their construction pad.  The pad will be the location where piling will be stockpiled as well as other construction staging.



May 15, 2019

South Bend's new elementary school build is moving forward.  Currently, contractors are surveying the building site in preparation for the approximate 180 piling that will be installed. 
At the same time, South Bend maintenance crews are removing our greenhouses and playground equipment.  I spoke with Rognlin's construction superintendent, Brandon Russell, today where he told me they hope to move piling in the week of June 3.  Rognlin's hopes to begin driving pile on June 10.